The Castle Group's Projects

 

ROEBLING BRIDGE REPLACEMENT

Design/Build

The abandoned steel railroad bridge at the Roebling Steel Plant crossing Crafts Creek in Roebling, New Jersey needed to be converted into a roadway bridge able to support construction vehicles up to 110,000 lbs. W.J. Castle P.E. & Associates P.C. was retained by WRS Infrastructure & Environment, Inc. in October 2008 to perform an in-depth inspection of the existing bridge. Once the analysis was complete, Castle designed the new bridge utilizing the existing main steel beams and the concrete substructure with modifications and repairs. Hydro-Marine Construction Co., Inc. performed the actual construction of the bridge.

 

Following cleaning of the existing beams, deteriorated portions of the beams were reinforced by attaching steel bent plates (6 foot long) to both sides at each end. Existing bearing plates were also deteriorated and replaced to accommodate the new spacing of the steel beams.  In order to save labor cost, a single continuous bearing plate was used at each abutment. New stringers, diaphragms, deck pans, and edge plates were installed as well as new steel guiderail and posts. The composite reinforced concrete bridge deck was built utilizing angle sections attached to the main steel beams. The concrete deck was poured in place in less than one day.

 

Hydro-Marine performed all of the construction aspects of the project including all repairs, removal of the existing structure, and installation of the new bridge structure. Removal of the existing structure began in November 2008, the deck was poured the first week in January 2009, and the bridge was open to traffic by January 23, 2009.

View as PDF>

 

 

Design & Installation of Main Bulkhead/Wave
Breaker @ Canal Point Marina

Bulkhead Design/Build

Location: Point Pleasant, New Jersey

 

W.J Castle, P.E. & Associates, P.C. was retained by the Canal Point Marina to design/build a new bulkhead at their facilities. The original bulkhead was undermined and deteriorated and no longer functioning as designed.

 

Castle’s repair design included installation of new composite sheeting in front of the existing timber bulkhead and installation of 21 additional 12” diameter timber piles to be placed between the existing deteriorated piles. However, the existing piles and walers were also utilized in the construction of the new bulkhead.

 

Upon completion of design and details, Hydro-Marine Construction Co., Inc. was retained to perform the actual construction of the new bulkhead. Approximately 290’ of new composite sheeting was installed with an additional 20 L.F. along the walkway.

 

Twenty-one new timber piles were installed along the bulkhead and three additional 10” diameter timber piles were installed near the walkway as per the client’s specification.

 

All work was completed by October 2008 at a cost of approximately $400,000.00.

 

 

GIRL SCOUT PEDESTRIAN BRIDGE

Design/Build

Location: Girl Scouts of Eastern Pennsylvania – Camp Laughing Waters Montgomery County, Pennsylvania

 

W.J. Castle, P.E. & Associates, P.C. & Hydro-Marine Construction Co., Inc. were retained to design and construct a new 140’-0” long pedestrian bridge for a Girl Scout camp located in Gilbertsville, PA. The client was redesigning the camp site to include a new route for pedestrians to cross Swamp Creek. W.J. Castle, P.E. & Associates, P.C., was responsible for all engineering and construction management of the bridge and foundations. This 140’-0” steel bridge was provided by “Eagle Bridge” of Canada and pre-fabricated into two modules and shipped to the site, ready for installation.  The bridge is 8 feet wide and was designed for both pedestrian (85#/S.F.) and small vehicle (10, 000 lbs). The total weight of the bridge is approximately
60,000 lbs.

 

Hydro-Marine Construction Co., Inc. was responsible for the construction from the start of the project to final installation. A foundation system using “Chance” Helical Piles was used in order to eliminate large spread footings. The construction of the bridge was started in April of 2008 and completed by June 2008 at a cost of $421,000.00. 

 

In March 2009 this project won the ACEC Distinguished Award for Pedestrian Bridge Design/Build.

 

Award Winning Projects

 

Projects Archive